OIL& GAS PLANT ENGINEERING PROJECTS BY ARSLAN ENGINERY PVT.LTD. | |||||
SR.NO | CLIENT | PROJECT | END CLIENT | SCOPE OF WORK | YEAR |
1 | SEL | PREPARATION OF TENTATIVE BOQ INCLUDE SKID BOQ, PIPING BOQ, SKID GA | Reliance Industries Ltd | SKID GA, SKID BOQ, PIPING BOQ | |
2013 | |||||
2 | SEL | CABLE TRAY SUPPORT | ONGC | STRUCTURAL DESIGN, ANALYSIS & DETAILING FOR CABLE TRAY SUPPORT | |
2013 | |||||
3 | SEL | NEELAM & HEERA PLATFORM | ONGC | BASIC ENGINEERING, OFFSITE PIPING,STRUCTURAL, ELECTRICAL & INSTRUMENTATION DESIGN DETAIING AND ANALYSIS | |
2013 | |||||
4 | L&T | 3D MODELING, PIPING AND SUPPORT | P&G | 3D MODELING,PIPING DETAILING, ROUTING, SUPPORT & STRESS ANALYSIS | |
2012 | |||||
5 | SEL | EARTHING AND LIGHTING WORK | ONGC | EARTH PIT CALCULATION, LAYOUT AND DRAWING | |
2013 | |||||
6 | SOPAN O&M | PIPING 3D MODEL, ISOMETIC, BOM | HPCL | PIPING 3D MODEL AND ISOMETRIC GENERATION AND BOM | |
2014 | |||||
7 | SOPAN O&M | PIPING 3D MODEL, ISOMETIC, BOM | BPCL | PIPING 3D MODEL AND ISOMETRIC GENERATION AND BOM | |
2014 | |||||
8 | SOPAN O&M | PIPING 3D MODEL, ISOMETIC, BOM | HPCL | PIPING 3D MODEL AND ISOMETRIC GENERATION AND BOM | |
9 | GAS PROCESSING FACILITIES, U.S. – RESOLUTE ENERGY | PIPING DESIGN, FULL CIVIL DESIGN, ELECTRICAL & CONTROL DESIGN & CONSTRUCTION SUPPORT | RESOLUTE ENERGY | ENGINEERING AND DRAFTING SERVICES FOR THE INSTALLATION OF AN 80 MMSCFD PROPANE REFRIGERATION PLANT AND A 60 MMSCFD DEHYDRATION UNIT AT AN EXISTING FACILITY. THE PROJECT DIRECTIVE IS TO UTILIZE DEHYDRATION, REFRIGERATION, AND EVENTUALLY A MEMBRANE PLANT TO CLEAN UP AND RECYCLE THE CO2, WHICH IS CURRENTLY BEING INJECTED INTO RESOLUTE ENERGY’S FIELDS FOR OIL RECOVERY. | |
2014 | |||||
10 | THIRD PARTY | DETAILED ENGINEERING AND DESIGN EQUIPMENT | U.S. ENCANA | DETAILED ENGINEERING AND DESIGN EQUIPMENT: WATER TANKS, TRANSFER INJECTION PUMPS, POWER GENERATION, AND TRUCK LOADING AND UNLOADING. | |
2013 | |||||
11 | THIRD PARTY | DESIGN & DETAILING | IOCL PANIPAT | DESIGN & DETAILING OF ONE NOS. CIRCULAR & ONE NOS. RECTANGULAR FIRED HEATER-STRUCTURAL, DUCTING & PIPING. | |
2014 | |||||
12 | THIRD PARTY | DESIGN & DETAILING | RELIANCE PETROLEUM LTD | DESIGN & DETAILING OF RELIEF KNOCKOUT DRUM, HYDROCARBON ABSORBER, VAPOR EXCHANGER, COMBINED VAPOR LIQUID CHILLER, REFRIGERANT ECONOMIZER. | |
2014 | |||||
PROCESS PLANT ENGINEERING PROJECTS By ARSLAN ENGINERY PVT.LTD. | YEAR | ||||
SR.NO | CLIENT | PROJECT | END CLIENT | SCOPE OF WORK | |
1 | AKER SOLUTION | KRISHNAPATANAM VEGETABLE OIL REFINERY | LD COMMODITIES INDIA PVT. LTD. | PIPING LAYOUT,ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO. | 2010 |
2 | KBK CHEM ENGG PVT LTD | 150 MTD ETHYL ACETATE PLANT | GNFC BHARUCH | 3D MODELING, PIPING LAYOUT,ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO, STRESS ANALYSIS | 2011 |
3 | XYTEL INDIA | PILOT PLANT MODEL | TAKREER | PIPING GA, 3D MODEL, BOM SUPPORT | 2009 |
4 | XYTEL INDIA | PILOT PLANT MODEL | GHARDA CHEMICALS | PIPING GA, 3D MODEL, BOM SUPPORT | 2009 |
5 | ULTRATECH CEMENT | BAG FILTER PIPING | ULTRATECH CEMENT | PIPING LAYO UT, ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO, STRESS ANALYSIS | 2012 |
6 | PRAJ INDUSTRIES | BREWERY PLANT | PIPING LAYO UT, ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO | 2012 | |
7 | PRAJ INDUSTRIES | PROCESS PLANT | RELIANCE | PIPING 3D MODELING IN PRO-PIPE, 2D PIPING LAYOUT, PIPING ISOMETRICS WITH BOM, SUPPORT DWG, MTO | 2013 |
8 | PRAJ INDUSTRIES | PROCESS PLANT | BIOCON MALAYSIA | PIPING 3D MODELING IN PRO-PIPE, 2D PIPING LAYOUT, PIPING ISOMETRICS WITH BOM, SUPPORT DWG, MTO | 2013 & 2015 |
9 | XYTEL INDIA | HEAT EXCHANGER PILOT PLANT | 3D MODELING,PIPING LAYO UT, ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO | 2014 | |
10 | XYTEL INDIA | POLY PROPYLENE PILOT PLANT | 3D MODELING,PIPING LAYO UT, ISOMETRICS DRG., MTO,SUPPOET GA & DETAILS WITH SUPPORT MTO | 2014 | |
11 | KBK CHEM ENGG PVT LTD | 60KLPD DISTILLERY PLANT | PROVIDING ONSITE 2 ENGINEER-PIPING ISOMETRIC, SUPPORT DETAILING WORK, STRUCTURAL | 2014 | |
12 | XYTEL INDIA | PLASTIC PYROLYSIS | SABIC | STRUCTURAL ANALYSIS, SKID DESIGN, MEMBER SIZING, CIVIL FOUNDATION,GA DRAWING, FABRICATION DRAWING | 2014 |
13 | SPX FLOW TECHNOLOGIES, INDIA | DAIRY DRYER PROJECT | PLANT ENGINEERING WORK-3D MODELING,PIPING ISOMETRIC, SUPPORT DETAILING WORK, STRUCTURAL | 2014 |
Plant Design Engineering by Arslan Enginery Pvt.Ltd. | |||||
Sr. No. | Client Name | Client’s P.O.Reference & Date | End Client | Project Description | |
1. | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/199-1002-10-2010 | Lurgi | ISO generation from back up including required set up,customization & regeneration tor minor corrections. | |
2 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/204-1025-11-2010 | ONGC | 1) Integration ot TEKLA to PDSFW,for three different models.2) To make Model intelligent so that it can be edited at any instant & do clash detection.3) Misc.support modelling for above structure. | |
3 | L & T Integrated Engineering Services,Chennai | LTIESPUR_10-11_1260-1 15-02-2011 | P&G USA | Design Engg Services- SP3D1 )As built of all piping as per red line mark up for chemical and fibre plant2) Equipment Modeling, ISO generation, layout extraction3) Stress Analysis of rerouted lines | |
4 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_0280-110-05-2011 | P&G USA | Engineering Consultancy Services1) Piping detailing and routing refering to P&ID2) Generating General Arrangement Drawings3) support customistion & placement of Pipe suppports | |
5 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_0621-114-06-2011 | P&G USA | As Builting of 250 field verified ISO for Goldrush project | |
6 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/232-11 14-07-2011 | ONGC | 1) Integration of TEKLA to PDSFW,for three different models.2) To make Model intelligent so that it can be edited at any instant & do clash detection.3) Misc.support modelling for above structure.4) To update misc.changes in model(if req.) | |
7 | L & T -Chiyoda Limited | WO/2011-12/8828-07-2011 | Shah Gas Development (UAE) | •Implimentation of SP3D•Piping specification customization which includes piping and instrument speciality (catalogue/symbols also) and nozzle data customization• Onsite support / trouble shooting to disciplines like Piping, Equipment, Instrument, Electrical, Civil & Structural• Piping support catalogue customization• Catalogue /specification customization for cable tray/raceway symbols• Symbols for Civil section libraries • Isometric template / Orthogen template customization • Report template customization • Any other activity which is required for smooth implementation of SP3D | |
8 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_1139-225-08-2011 | P&G USA | Goldrush Phase II Scope Document ( Engg of Following)1. Bleach Broke Area2. City Water Break Tank (27D-502) -3. Existing Plant Fresh Water Tank (27D-501)4. Boilers5. Wastewater Headers 6. Cooling Tower 7. Air Compressors | |
9 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/236-11 08-09-2011 | ONGC | 1) Isomertic Extraction of 50(+/-3) lines from PDS.2) Import the FD fan Structure with Intelligency. | |
10 | Lahmeryer International (India) Pvt.Ltd. | GEDE10135/ELEC/0112-09-2011 | Qurayyah CCPP Project (Saudi Electricity Company) | SPEL work for support to all modules of SPEL including modeling Preparing master Schematic drawings, Cable scheduling reports, Cable tray Loading reports, Symbol Customisation. | |
11 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_1966-103-11-2011 | P&G USA | GoldRush Phase II Extension Scope1. Resolutions of 100 Nos. To-Do-List errors in GoldRush-II2. Customization for 42 Nos. of To-Do-List errors. | |
12 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_1967-103-11-2011 | P&G USA | Goldrush Phase II Extension Scope1. Copy 25 lines from BC1 to BC-32. Isometric extraction of 25 lines | |
13 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_1968-1 03-11-2011 | P&G USA | GoldRush Phase II Extension Scope1. Report Customization.2. Engineering & Design of New Bleach Broke Lines.3. Engineering & Design of Condensate Flush Tank & Piping in Boiler Room.4. Engineering & Design of Condensate Tank & Piping.5. Engineering & Design of Waste water Tank & Piping. 6. Deletion of Outside Area ( All Tanks, Piping & Structures). 7. All OGC Work of Phase-I. | |
14 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/245-11 09-11-2011 | ONGC | Isomertic Extraction of 26 (+/-3) lines from Backup. | |
15 | Prothious Engineering Services | PESPL/MUM/2011-2012/23 | JGC | Detail Enaineerina °f C°lumn. Heat Bc^natsf & Tank Column:-1) Mechanical Calculation2) General Arrangement drawing with Nozzle orientation.3) Fabrication details with BOM.Heat-Exchanger:-1) Mechanical Calculation 2) General Arrangement drawing with Nozzle orientation. 3) Fabrication details with BOM. Drum:- 1) Mechanical Calculation 2) General Arrangement drawing with Nozzle orientation. 3) Fabrication details with BOM. | |
16 | Prothious Engineering Services | PESPL/MUM/2011-2012/31 | JGC | Piping Engineering services1) Preparation of Plot Plan2) Preparation of Equipment Layout.3) Preparetion of Piping Layout.4) Nozzle orientation details. | |
17 | Saipem India Projects | Contract No. 681197 | Shah Gas Development (UAE) | INSOURCING OF SP3D DESIGNERS IN SIP OFFICE FOR SHAH GAS | |
PROJECTDesign the Lines of the Packages as per the input provided by the package vendors.- Design the small bore lines as per the guidelines.- Design of support’s based on CONTRACTOR Engineer’s guidelines.- Update the piping arrangement based on the comments from CONTRACTOR.- Update the equipment based on vendor information . . To extract isometrics and update the comments during isometric extraction. | |||||
18 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/254-1223-01-2012 | Cameroon Sonara | 3D MODELING FOR FM boiler in PDMS Boiler parameters: 120 TPH, 106 Barg, 5l0±5 “C, gas fired single drum, bottom supported boiler.SOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Import of structure from TEKLA and miscleneos structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. | |
19 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/253-1223-01-2012 | Gail Vijaypur (EIL) | 3D MODELING FOR HRSG Boiler in PDMS Boiler parameters: 120 TPH, 106 Barg, 5l0± 5 “C, gas fired single drum, bottom supported boiler.SOW: Same as Above Boiler |
20 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/252-1223-01-2012 | Gail Vijaypur (EIL) | 3D MODELING FOR RADIENT Boiler in PDMS Boiler parameters: 120 TPH, 106 Barg, 5l0±5 “C, gas fired single drum, bottom supported boiler.SOW: Same as Above Boiler | |
21 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_11-12_3073-224-02-2012 | P&G USA | GoldRush-II All Plant Large Bore ISO Extractions | |
22 | Reliance Infrasructure Limited | SERI/ES3/2353269423-02-2012 | Reliance Infrasructure Limited | Creation of SPEL Report of “Typical POWER” and “Typical Control” by using SmartPlant Electrical | |
23 | Emerson Process Management India Pvt.Ltd. | OW 5550204 13-02-2012 | Gail Vijaypur (EIL) | Instrument Hook Up Design in PDMS. | |
24 | L & T Integrated Engineering Services,Vadodara. | LTIESPUR_11-12_3263-112-03-2012 | Kiewit Power | Creation of P&ID(4 nos) using SPP&ID: Symbol Creation and databse customisaiton, Drafting P&IDs referring AutoCAD P&ID, Report extractions like Valve list, Equipment list, instrument lists, Line lists. | |
25 | GOLLA ENGINEERING PRIVATE LIMITED | GEPL/CTS/P0/2012/04/02-01 | Technip (IOCL Mathura Refinary Project) | • Provision of three numbers of designers at respective job locations for minimum two month duration.• To update the 3D model (Piping only) as per Client comments.• To incorporate the new lines in the model.• To incorporate all comments by Golla.• To extract the Isometrics and GAD from the model.• To do the Pipe supporting in model as detailed by client. • Updating the 3D model in PDS and extracting drawings. | |
26 | Lahmeryer International (India) Pvt.Ltd. | LII/GEDE12008/WO/TAU2012-13/0039-04-2012 | Wadi, Sharourah, Nagarn | SP3D Designing work: Refering AutoCAD Layout Pipe routing and Designing, Equipment designing, Support Placement, ISO Extraction, GAD Extraction. | |
27 | Lahmeryer International (India) Pvt.Ltd. | LII/GEDE11132/WO/TAL/2012-13/0029-04-2012 | Wadi, Sharourah, Nagarn | SP3D Designing work: Refering AutoCAD Layout Pipe routing and Designing, Equipment Designing, Support Placement, ISO Extraction, GAD Extraction. | |
28 | L & T Integrated Engineering Services,Vadodara. | LTIESPUR_12-13_0255-101-05-2012 | Kiewit Power | Creation of P&ID(2 nos) using SPP&ID on ANSI-D(22″x 34″) Size | |
29 | L & T Integrated Engineering Services,Vadodara. | LTIESPUR_12-13_0299-108-05-2012 | Kiewit Power | 1) Setup and Administration of the Project using SP3D Version – V9 (SP1).2) Piping Specification Customization with SP3D Out of Box Symbols (4no.).3) Structure designing using SP3D default library.4) Equipment designing (18 nos).6) Piping designing.7) Isometric Drawing Border Template Customization with Default Package. 8) GAD Border Template Customization using default Graphic Rule. 9) Isometric and GAD Extraction. 10) Default Report extraction of Valve List and Line List. | |
30 | Emerson Process Management India Pvt.Ltd. | OW 5550234 14-05-2012 | Gail Vijaypur (EIL) | Instrument Hook Up Design in PDMS | |
31 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_12-13_0363-115-05-2012 | P&G USA | Piping Spec customization in SP3D | |
32 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_12-13_0362-115-05-2012 | P&G USA | To execute the SP3D portion of the WW Neutralization project, L&T will work in a new S3PD plant model, “GoldrushI_LT” (Project model). This model will only contain:The existing plant items that has to modify:1) Neutralization Tanks #1, #2, #3, and #42) Pipeline SUAE-510144A view-only Reference3D (R3D) model of the existing tank farm area, for coordination of new design with existing plant. | |
33 | Emerson Process Management India Pvt.Ltd. | OW 5550265 30-Jun-12 | Gail Pata (EIL) | Instrument Hook Up Design in PDMS. | |
34 | L & T Integrated Engineering Services,Vadodara. | LTIESPUR_12-13_1069-115-05-2012 | Kiewit Power | Piping Stress Analysis of Pipelines within the SKID considering Wind, Seismic,Snow load as per provided data.Dynamic Analysis of PSV Lines. | |
35 | Emerson Process Management India Pvt.Ltd. | OW 5550277 25-Jul-12 | Gail Pata (EIL) | Instrument Hook Up Design in PDMS | |
36 | L & T Integrated Engineering Services,Chennai. | LTIESPUR_12-13_1581-1 12-09-2012 | P&G USA | SP3D Additional Scope in Neutralization Project | |
37 | Reliance Corporate IT Park Ltd. | XM9/31068785 11-10-2012 | RIL | Peligen forge Support Library Customisation as per Reliance standard support library (300 Supports) | |
38 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/302-1209-10-2012 | Gail Vijaypur (EIL) | 3D MODEI ING FOR HRSG RoilerBoiler parameters: 120 TPH, 119 Barg, 5l0±5 “C, gas fired single drum, bottom supported boiler.SOW: same as Boiler scope mentioned above SR. No.18 | |
39 | Triveni Engineering & Industries Ltd. | Project No: PXD-972 | Triveni Engineering & Industries Ltd. (EIL) | Engineering & Design of DM WATER PLANT AND CPU FOR GAIL PETROCHEMICAL COMPLEX-II By Using PDMS SOW: Structure modeling, Equipment Modeling, Spec customisation, Valve and instrument symbol customisation, Pipe routing refering P&ID, Supporting of lines, IFC ISO extraction, Layout extraction. | |
40 | PLANTECH CONSULTANTS PVT.LTD | PO/CTS/324-1331-01-2013 | SABIC | SP3D MODEL ING FOR WHRRTail Gas Fired WHRBSOW: same as Boiler scope mentioned above SR. No.18 | |
41 | Emerson Process Management India Pvt.Ltd. | OW 84140905/139 21-02-2013 | Gail Pata (EIL) | Instrument Hook Up Design in PDMS | |
42 | ATLAS COPCO(INDIA) Ltd | PR No 041 07-03-2013 | AT LA S CO P CO ( 1 ND I A) Ltd | 3D Modeling of skid, GAD, BOM, ISO Extraction | |
43 | PT ARIA PERSADA Indonesia | SO# 7432002265 | PT ARIA PERSADA Indonesia (Wilmar) | HVAC Engineering & Design Consultancy Services for pressurized control room. | |
44 | MEIP Delhi | MEIP-PIPING-2013-38 | MITSUBISHI | Deputation of SP3D Administrator & Modelers | On going Project |
45 | ATLAS COPCO(INDIA) Ltd | 75473 | ATLAS COPCO(INDIA) Ltd | Design of pressure Vessel by using PV Elite | |
46 | Aquatech Systems (Asia) Pvt. Ltd. | -42140026/1314 | Aquatech Systems (Asia) Pvt. Ltd. | Pre-bid Engineering Service for Desalination Plant of California | |
47 | Transtech Projects Pvt Ltd | PO NO- 20 | SABIC | Deputation of SP3D Administrator & Modelers | |
48 | VA Tech Wabag Limited | MBG- PO-13565/10P27Mdt | Reliance Industries Limited | Provide PDS Administration Services for their exiting project like Spec customization, ISO, GAD template customization, etc. Total Man hours consumed for this work is 400. | |
49 | VA Tech Wabag Limited | CHANDAN-TECH-SOLUTONS-MBG-PO-14181-PRICED-WO | Reliance Industries Limited | Provide PDS Modeling Services for their exiting project. Total Man hours consumed for this work is 1100. |
50 | Transtech Projects Pvt Ltd | PO NO- 44 | SABIC | Deputation of SP3D Administrator & Modelers | ||
51 | PT Wilmar Nabati Indonesia | SO# 8102157821 | PT Wilmar Nabati Indonesia (Wilmar) | HVAC Engineering & Design Consultancy Services for four sites which is PFAD, FAL/Fatty Alcohol, BD-3 &4, BD-5. | ||
52 | ATLAS COPCO(INDIA) Ltd | 75473 | ATLAS COPCO(INDIA) Ltd | Design & ASME calculations of manifold by using PV Elite | ||
53 | Aquatech Systems (Asia) Pvt. Ltd. | AE-1035-42110624/1314 | RIL | PDS 3D Modeling Services for Reliance six units which was awarded to Aquatech. Total Man hours consumed for this work is 3500. | ||
54 | Transtech Projects Pvt Ltd | PO NO- 52 | SABIC | Deputation of SP3D Administrator & Modelers | ||
55 | Transtech Projects Pvt Ltd | PO NO- 62 | SABIC | Deputation of SP3D Administrator & Modelers | ||
56 | Transtech Projects Pvt Ltd | PO NO- 74 | SABIC | Deputation of SP3D Administrator & Modelers | On going Project | |
57 | ISGEC Heavy Engineering Ltd | 106341/JE1502 | ISGEC | PDMS 3D Modeling Design Services for Auxilary Boiler: | On going Project | |
SOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Import of structure from TEKLA and miscleneos structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 3700. | ||||||
58 | Anewa Engineering Pvt Ltd | AEPL/ADM/2013-14/PO/88 | Technip (Abu Dhabi) | Deputation of PDS Designer at Technip (Abu Dhabi) Location | ||
59 | Ingenero Technologies India Pvt Ltd | ING/CTS/26112013/00 | Ingenero | LFM 3D Modeling Services | ||
60 | Nipunn Engineering & TechnoConsultant Pvt Ltd | NETC/ACC/2014-15/0001/07.01.2014 | Nipunn | Deputation of PDMS Desigenr at Nipunn Gurgaon Office | ||
61 | PLANTECH CONSULTANTS PVT.LTD | PO/ENGG/CTS/145 | RIL | PDS 3D Modeling Services for Fuel Oil HeaterSOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 750. | On going Project | |
62 | PLANTECH CONSULTANTS PVT.LTD | PO/ENGG/CTS/132 | RIL | PDS 3D Modeling Services for HRSG Boiler 275 TPHSOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 1500. | On going Project | |
63 | PLANTECH CONSULTANTS PVT.LTD | PO/ENGG/CTS/141 | RIL | PDS 3D Modeling Services for Auxilary Boiler 2 X 250 TPHSOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 1500. | On going Project | |
64 | PLANTECH CONSULTANTS PVT.LTD | PO/ENGG/CTS/133 | BPCL | PDMS 3D Modeling Services for FGC (Flue Gas Cooler):SOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 1100. | On going Project | |
65 | PLANTECH CONSULTANTS PVT.LTD | PO/ENGG/CTS/142 | BPCL | PDMS 3D Modeling Services for HRSG Boiler 3 X 110 TPHSOW: Equipment Modeling and pressure part modeling as per client supplied drawings. Piping specification customisaction, Insrument and speciality symbol customisaion. Piping detailing and modeling refering P&IDs and 2 D Layouts. Structure modeling, extraction of various Plans and elevation of structure.Support modeling and placement refering to stress isometrics. support selection refering to standard provided by the client. Clash detection and resolution. Isometrics generation and extraction. Piping layout 2 D extraction, General Arrangement Drawing Extraction. Equipment Fabrication drawings. Various reports like nozzle report, line list, valve list, instrument list, Equipment list, each line MTO, bulk MTO. Cable tray routing and extraction of layout. Total Man hours considered for this work is 1800. | On going Project | |
66 | Aquatech Systems (Asia) Pvt. Ltd. | AE/1041/52110100/14-15 | RIL | PDS 3D Modeling Services for Reliance six units which was awarded to Aquatech. Total Man hours considered for this work is 4500. | On going Project | |
67 | VA Tech Wabag Limited | IWG- PO-6125/10P56 | Reliance Industries Limited | Provide PDS 3D Modeling Services for Reliance J3 expansion DTA project. Total Man hours considered for this work is 6000. | On going Project | |
68 | VA Tech Wabag Limited | IWG-PO-6120/10P54I | Reliance Industries Limited | Provide PDS 3D Modeling Services for Reliance J3 expansion SEZ TTP project. Total Man hours considered for this work is 3000. | On going Project | |
69 | VA Tech Wabag Limited | IWG-PO-6121/10P55I | Reliance Industries Limited | Provide PDS 3D Modeling Services for Reliance J3 expansion SEZ ETP project. Total Man hours considered for this work is 2500. | On going Project |
70 | VA Tech Wabag Limited | MBG-PO-15188/10P27M | Reliance Industries Limited | Provide PDS 3D Modeling Services for their exiting RIL Dahej project. Total Man hours consumed for this work is 700. | ||
71 | Tecton Engineering & Construction LLC | TEC/CTEFE121210/WO/1002 | ZADCO Project No.P8362 | Provide Services related to Smart Plant 3D, Smart Plant P&ID, Smart Plant Instrumentation & Smart Plant Electircal for their ZADCO Project which is awarded to Tecton. Total Man hours considered for this work is 17600 for all Smart Plant Related Work. | On going Project | |
72 | Tecton Engineering & Construction LLC | TEC/CTEFE121210/WO/1003 | ZADCO Project No.P8362 | Deptation of Smart Plant 3D Admin, Smart Plant P&ID Admin, Smart Plant Instrumentation Admin and Smart Plant Electrical Admin at Tecton Abu Dhabi office for smooth execution of ZADCO Project. | On going Project | |
73 | Osmoflo Engineering Services Pvt Ltd | OESPL/PO/14-15/0011 | Inventor 3D Modeling Austrilia Project | Deptation of AutoCAD Inventor Designer At Osmoflo office for the period of 12 months. | On going Project | |
74 | AVEVA India | Aveva/Aug/14/001 | JSPL | Laser Sacnning of Turbine Building and Intillegent 3D modeling for this TG building and cooling towers. Manhours estimated for this job are 1800 | On going Project | |
75 | AVEVA India | Damodar Valley Corporation | Customization of 400 templates for Power plant and Auxillaries. Manhours required for this Job are 2200 | On going Project | ||
76 | Sandvik Asia Pvt Ltd | S-171021 | BPCL | PDS 3D Modeling Services for IREP BPCL Kochi – Sulphur Forming & Handling System Integrated Refining Expansion Project. Total Man hours considered for this work is 2500. | On going Project | |
Software Development | ||||||
1 | Volkswagen India Private Limited | 8000014185 | Volkswagen India Private Limited | Shimming Software for Pilot Hall | ||
2 | Volkswagen India Private Limited | 8000015326 | Volkswagen India Private Limited | Supplier Chargeback Management | ||
Training | ||||||
1 | IBIC Engineering | IBIC/IT/ PO/35/2010-11 29-08-2010 | Toyo Thai (Thailand) | Peligen Forge support Modeler(Thailand) | ||
2 | IBIC Engineering | IBIC/IT/PO/41/2010-1103-09-2010 | Thai Wo Ree (Thailand) | SP3DReference Data Engg. Services & Project set-up,PBS SET-UP Generation of Drawings-GA,ISOs MTO Generation Loading of Piping Specs as size dependent specs. | ||
3 | Lahmeryer International (India) Pvt.Ltd. | REF:LII/PUR/BMV/10-11/Training 02/11/2010 | Lahmeryer International (India) Pvt.Ltd. | SP3D-Equipment & Piping Reference Data SP3D-Structural Reference Data SP3D-Drawing Customization SP3D- Electrical Reference Data | ||
4 | Saipem India Projects | SIP/HR/TRG/LOA-004/201104-01-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
5 | Saipem India Projects | SIP/HR/TRG/LOA-005/201125-01-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
6 | Saipem India Projects | SIP/HR/TRG/LOA-007/201102-02-2011 | Saipem India Projects | SP3D-Smart Plant 3D electrical Modeling, Tray Support Modeling, Drawing Creation and Common Tasks | ||
7 | Saipem India Projects | SIP/HR/TRG/LOA-010/201101-03-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
8 | Saipem India Projects | SIP/HR/TRG/LOA-011/2011 09-03-2011 | Saipem India Projects | SP3D-Civil Modeling/ drawing Creation TSMP1006 | ||
9 | Saipem India Projects | SIP/HR/TRG/LOA-013/201118-04-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
10 | Saipem India Projects | SIP/HR/TRG/LOA-016/201120-04-2011 | Saipem India Projects | SP3D-Civil Modeling | ||
11 | Saipem India Projects | SIP/HR/TRG/LOA-015/201125-04-2011 | Saipem India Projects | SP3D-Electrical & Instrumentation Modeling | ||
12 | Saipem India Projects | SIP/HR/TRG/LOA-017/201112-05-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling | ||
13 | Saipem India Projects | SIP/HR/TRG/LOA-025/201125-07-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
14 | Saipem India Projects | SIP/HR/TRG/LOA-038/201128-11-2011 | Saipem India Projects | SP3D-Piping & Equipment Modeling TSMP1001/Drawing Creation TSMP1006 | ||
15 | L & T -Chiyoda Limited | 064/2011-1223-06-2011 | L & T -Chiyoda Limited | Training on1) SP3D piping & equipment modeling2) SP3D electrical modeling3) SP3D Structural Modeling4) SP3D drawing creation5) SP3D drawing Customization 6) SP3D Isometric Drawings 7) SP3D Report Customization 8)SP3D Set up & Administration 9) SP3D Equipment & Piping Reference Data 10) SP3D Electrical Reference Data 11) SP3D Structral Reference Data | ||
16 | Linde Engineering India Pvt. Ltd. | CTSPUMK/Linde/0101-08-2011 | Linde Engineering India Pvt. Ltd. | SP3D Administration Training | ||
17 | Linde Engineering India Pvt. Ltd. | CTSPL/MK/Linde/02 07-09-2011 | Linde Engineering India Pvt. Ltd. | SP3D Administration Training | ||
18 | L & T Integrated Engineering Services,Vadodara | LTIESPUR_11-12_3391-227-03-2012 | L & T Integrated Engineering Services,Vadodara | SPEL user level Training | ||
19 | National Petroleum Construction Company(NPCC) | 24821 | National Petroleum ConstructionCompany(NPCC Abu Dhabi) | Smart Plant 3D Software Training (SP3D) | ||
20 | Reliance Corporate IT Park Ltd. | XM9/31068106 01-10-2012 | RIL | Training & Impletation on SPP&ID & SPEL: Creating SPP&IDs, Drawing Manager. Support: Database creation and Project raising, Database Customistion, Report Customisation, Parametric Symbols, Insulation Spec Customisation. | ||
21 | Fluor Daniel India Pvt Ltd Gurgaon (Through Plant ITS Hyedrabad) | PTIS-WO-131202001 | Fluor Daniel India Pvt Ltd | Hangers & Support part assembly creation & Drawing Customization training. | ||